CAT 2009 Results Declared, Check Now !
Quantitative Aptitude > Time and Work
Practice Tests
Add Comment Bookmark share + Refresher MaterialFree Online Preparation for CAT 2009 with Minglebox e-CAT Prep. Cover basic concepts of Time and Work under Quantitative Aptitude for MBA Entrance Exam Preparation with Study material, solved examples and tests prepared by CAT coaching experts. If a person A can do a piece of work in 'a' days, then working at the same uniform speed A will do For example,
Working together – If working alone can do some work in 'a' days and if another person B working alone can do it in 'b' days , then if A and B start working together the amount of work done by A & B in one day =
Therefore total work is done by A and B working together in
Note: Remember it is work done that is additive and not number of days.
The LCM technique
If A completes a work in 'a' days working alone and B completes it in 'b' days working alone, then intended of assuming the work as 1 unit we can assume total work to be LCM of (a,b) this will avoid the fraction in the calculation.
Proportionality (concept of efficiency )
If A is thrice as efficient as B then if A takes 12 days to complete a work then B will take relative efficiency of team member is given the most suitable approach is to consider the capacities of each team member in terms of any given team member. Amount of Work done is directly proportional number of person employed to do the work and days worked. If amount of work is constant then number of days taken to complete the work is inversely proportional to days taken. Men , Women and children working in a given project.
Solved Examples Question
If work can be done in 10 days by 4 men or 6 women or 10 children. How many days are required for 3 men , 8 women and 6 days to complete it? Solution
1 Man will take 40 days , hence 3 men will take 40/3 days to complete it 1 women will take 60 days, hence 8 women will take 60/8 days 1 child will take 100 days , hence 6 days will take 100/6 days
then total time taken if they all worked together is =
Question A house can be built by A in 50 days and B can demolish it in 60 days . If A and B work on alternative days , in how many days will the house be built , assuming A stars first and once house is built completely B days not demolish it? Solution In 2 days cycle amount of work done = the work in one days , hence if work done is less then
In two days amount of work done is
588 days work left to be done on
Add CommentComments
|
|


jadhav4558 : great teaching...confidence booster
sandeep8677 : really,the level of question is not like CAT///and there are few mistakes in question paper
ravipal2551 : i am unable to take the test sir please help me
shanty9518 : good question
fahim4644 : This is really helpful for CAT preparer.
sayanti7664 : its quite surprising nd innovative
amit8752 : mast hai mamu
shrikant820 : Level of tests are quit good!!!!!!
pramodh3050 : PRAMODH47:there are some mistakes at the end of test....please clarifiy that
nithya1346 : It was very useful.But there are some mistakes in the explanations provided at the end of the test...Please check that out.
atul2777 : Hi guyz! I just want 2 say that the level of the questions of papers are not upto cat level....!
thanx!
madydilse : hi
there are some mistakes in the tests...i mean to say there are some mistakes in the questions...please check that out...and i want you to enhance the level of the tests.
thank you!!
gauravkokraaggarwal : its so good for that person who really want to do MBA And it will help him so much.....
thank you and your team very much:
GAURAV KOKRA (BHIWANI)
rahul3954 : the questions here are good and very useful to us.Thank a lot minglebox.